Aston Villa Football Club – Phase 3 Works
Complex structural alterations, controlled demolition and reinforced concrete works across the Trinity Road Stand and South West Corner, carefully coordinated around Villa Park’s operational and fixture programme.
Location
Birmingham
Sector
Sports and Stadia
Completion
2026
Package
Structural alterations, groundworks and RC works.
Package Value
> £1 million
Project Overview
ECS Group delivered a complex programme of structural alterations, controlled demolition, groundworks and reinforced concrete construction across the Trinity Road Stand and South West Corner of Villa Park. Part of ECS Group’s continuing involvement in the phased redevelopment of Villa Park.
The works included extensive alterations to the existing stadium terraces, together with new reinforced concrete foundations, ground beams, raft slabs, drainage and service infrastructure.
Key Scope of Works
• Precision saw-cutting and controlled demolition
• Crane-assisted removal of reinforced concrete sections
• Alterations to terraces, stairs, gangways and vomitories
• Deep reinforced concrete foundations and ground beams
• Reinforced concrete raft and overlay slabs
• Temporary propping and structural support works
• Drainage, ducting and concrete repairs
Project Delivery
The works required careful coordination around restricted access, crane operations, road closures and interfaces with the existing stadium. Selected works were undertaken between fixtures, with the principal structural alterations delivered during the close-season programme.